Quesnel, BC | Our most technically demanding scaffold to date
The Challenge
The Johnston Street Bridge in Quesnel needed coating work carried on through a BC winter. Paint has to cure, and the environment under the bridge needs protecting. It is our most technically demanding scaffold to date.
The Solution
We built the access and enclosure to the engineer's plans, with independent rolling roofs so the coaters could work in a clean, controlled space and the quality of the coating was protected.
The Result
Enclosing just the active work zone, instead of the whole structure, meant 45% less scaffold rental and labour for our client, and winter didn't stop the project.
On site
Enclosures | Temporary roofs | Complex access